Reasons for an Accurate Peak Heating Demand Calculation
An accurate heat
(and cooling) loading calculation is often overlooked in the building
and/or design process.
We highly
recommend that a professional
heat/cooling load calculation/modeling is performed for every
potential Ground Source installation. The information and
recommendations from this exercise will save you money in both on
going operating and initial installation cost.
The reasons
why:
-
A Ground Source
System in order to run at the highest efficiency must be sized to
the application as closely as possible. This is to prevent the
Ground Source system from “short cycling” (turning the
compressor on and off in a short time frame). Short
cycling means less efficiency, higher running costs.
-
Bigger does not
mean better. A larger Ground Source System will not
do the job easier and more efficiently.
-
If the Ground Source
System is too small the there will be inadequate heating/cooling for
the building.
-
A Ground Source
System that is too large will cost more to
purchase, install and operate.
-
Peak building
heat/cooling demand determines the exact size (kw) of the WaterFurnace unit.
-
The size/length
of the ground loop is directly related the size (kw) of the unit(s)
selected. Larger the kw the larger theground loop.
-
Different
buildings use very different construction
materials and methods. This means the heating/cooling requirements
can vary wildly from building to building. H1 (NZ minimum standard) is typically 80-100w/m² - In many cases this can be vasty improved for little construction cost.
-
If the peak heat demand is guessed there will be a percentage allowance (typically 20-30%) built in to ensure that the system meets peak demand. The result, you pay for a 20-30% bigger system than is required, no matter what sort it is.
-
An accurate
heat load calculation/modeling will normally pay for itself
immediately, with the operating savings and reduced installation
costs. e.g. a smaller, correctly sized ground loop and WaterFurnace unit
-
Increased
in building insulation and/or sealing is often an option. The
capital investment in added insulation and air retention is often less than the captial cost difference between smaller and larger units.
-
A professional heat
load calculation can cost from $300 to over $5000 for a very large
multi faceted building.
-
For an average new
building the cost is usually between $300-1700, dependant on the
detail of the data supplied by the client.
Example
of buildings of the same size with differing heating requirements:
| Building Floor Area m² |
Heating Watts / m² |
Total Building kW |
|
|
|
| 200 |
200 |
40 |
| 200 |
150 |
30 |
| 200 |
100 |
20 |
| 200 |
80 |
16 |
| 200 |
50 |
10 |
| 200 |
30 |
6 |
Yellow = Aprox minimum (H1) insulation for New Zealand new homes.
Annual running cost estimate:
| System Size kW |
Ground Source |
Diesel |
Electricity |
LPG |
|
|
|
|
|
| 40 |
$3,124.00 |
$8,496.00 |
$12,496.00 |
$13,122.00 |
| 30 |
$2,343.00 |
$6,372.00 |
$9,372.00 |
$9,841.50 |
| 20 |
$1,562.00 |
$4,248.00 |
$6,248.00 |
$6,561.00 |
| 16 |
$1,249.60 |
$3,398.40 |
$4,998.40 |
$5,248.80 |
| 10 |
$781.00 |
$2,124.00 |
$3,124.00 |
$3,280.50 |
| 6 |
$468.60 |
$1,274.40 |
$1,874.40 |
$1,968.30 |
Estimated COP's: Ground Source 4.0, Diesel 0.86, Electricity 1.0, LPG 0.90
Fuel Cost: Electricity$0.22kW/hr, Diesel $1.20/l, LPG $1.35/l
Indication of Ground Source Base Cost:
System size kW
|
Trench Length m
|
Loop Estimate
|
WaterFurnace Unit(s)
|
| 40 |
570 |
$17,500 |
$34,000 |
| 30 |
430 |
$10,500 |
$26,000 |
| 20 |
290 |
$8,200 |
$16,700 |
| 16 |
220 |
$7,000 |
$15,000 |
| 10 |
150 |
$5,700 |
$13,000 |
| 6 |
90 |
$4,600 |
$9,500 |
Note: Cost is indicative only. Items such as trenching/excavation, travel etc are not included.
This
information is produced as a guide only. Although every
effort has been made to ensure this information is accurate and
up-to-date, Ground Source and/or its principals or representatives
cannot be held responsible for errors, omissions or inaccuracies that
maybe present.
©Ground Source Limited 2010
|
|
|
|
|